Status Report 10Sep21
Rigid Constructors Dredging Contractor
Daniel Garza Project Manager - HDR Engineering, Inc, Owner’s-Engineer
The repair of the pump shaft/bearings is underway, and the earliest it will be complete will be on FRI 10Sep21. I expect that it will take 2-3 days to have the repaired part back onsite, and then one day to reinstall and test. I don’t expect that we’ll begin dredging operations until early next week.