The Dredge Report - 25 Aug 21
Posted on Aug 28th, 2021

Photo Jason Allen 8-24-21
 
Status Report 25Aug21
HDR Engineering, Inc. Contractor
Daniel Garza, Project Manager
  • Contractor has conducted dredging operations for 11 days 
  • Dredged approximately 50,679 CY (Cubic Yards) of material = approximately 14% of the total expected CY
  • Traveled about 2,775 LF (Linear feet) along project centerline = 29% of the overall project length of 9,700 LF. Note the apparent discrepancy between the CY and LF is due to significantly more material at the south end of the project (sandbar area) as compared to the north end of the river.
  • Project Manager Garza also included in his report this Link to description of Cutter Section Dredge and how it works. This is the type of dredge being used although much much smaller than the one seen in the video, but the principles are the same.