The Dredge Report - 3/18/22
Posted on Mar 18th, 2022

 
Photo Will Frederick
Mouth of the river on Jan 22, 2022.
 
Status Report 18Mar22
Rigid Constructors - Dredging Contractor
Daniel Garza Project Manager - HDR Engineering, Inc, Owner’s-Engineer
 
NO CHANGE since March 2nd report.
LF(Linear Feet) = 8,280 (85.4% of 9,700)
CY (Cubic Yards) = 374,349 (97.6% of 383,650)
 
There was no significant dredging operations over the last two weeks. Due to high waves and strong tides, Rigid has not dredged since Wed March 2, 2022.
 