The Dredge Report - 3/11/22
Posted on Mar 11th, 2022
Photo Jason Allen

No map of progress furnished this week...so near yet so far, an empty Gulf waits.
Status Report 11Mar22
Rigid Constructors - Dredging Contractor
Daniel Garza Project Manager - HDR Engineering, Inc, Owner’s-Engineer
NOTE: no change of the metrics since previous March 2nd report
Based on daily reports, the following metrics have been calculated
LF (Linear Feet) = 8,280 (85.4% of 9,700)
CY (Cubic Yards) = 366,855 (95.6% of 383,650)
There was no dredging over the past week. Due to high waves and strong tides, Rigid has not dredged since Wed March 2, 2022. Rigid provided an update to me yesterday indicating that this Saturday could possibly be the start of the next window to begin dredging.