The Dredge Report - 2/16/22
Posted on Feb 18th, 2022
Photo Bert Smith



Map shows section of river worked Thu 2/10/22 thru Wed 2/16/22
Status Report 16Feb22
Rigid Constructors - Dredging Contractor
Daniel Garza Project Manager - HDR Engineering, Inc, Owner’s-Engineer
Based on daily reports, the following metrics have been calculated:
LF (Linear Feet) = 8,280 (85.4% of 9,700)
CY (Cubic Yards) = 366,855 (95.6% of 383,650)- Total volume includes original CY of 362,163 + 21,847 CY of additional material.
Rigid achieved another milestone – they have moved beyond the eastern shoreline and made it into the Gulf of Mexico.
There were two days this week (02/16 and 02/16) where waves did not allow for dredging.
Currently at STA. 82+80, Rigid’s updated schedule has a dredging completion date of approximately the second or third week of March 2022.
The County will issue a change order for the additional material.