The Dredge Report 2/2/22
Posted on Feb 4th, 2022
Map shows sections of river reworked thu Wed 2/2/22
Status Report 2Feb22
Rigid Constructors - Dredging Contractor
Daniel Garza Project Manager - HDR Engineering, Inc, Owner’s-Engineer
Based on daily reports, the following metrics have been calculated:
LF (Linear Feet) = 7,740 (79.8% of 9,700)
CY Cubic Yards) = 349,105 (96.4% of 362,163) - Total volume will be adjusted when change order to finalized.
Rigid has been able to dredge almost continuously at the north end of the project without the challenges of waves and currents experienced at the south end. On Tuesday February 1, 2022, they completed the dredging to STA 0+00, which is another milestone.
Rigid is now making their way back south, picking up any small mounds and missed areas. They will make their way south, clearing material as the go, and push to finish the project at the most southern station, STA 97+00.
The County continues in discussions with Rigid regarding a change order for the additional material and additional days has been developed.