The Dredge Report - 11/12/21
Posted on Nov 12th, 2021

 
Photo Jason Allen 11-9-21
The Yellow Fin dredge displays its white light at dusk indicating it's a powered vessel at anchor.
 
Section of completed dredging from Sat 11/06 to Wed 11/10
 
Status Report 12Nov21
Rigid Constructors Dredging Contractor
Daniel Garza Project Manager - HDR Engineering, Inc, Owner’s-Engineer
 
Based on daily reports, the following metrics have been calculatd
LF (Linear Feet) = 7,875 (81.2% of 9,700)
CY (Cubic Yards) = 222,121 (61.3% of 362,163)
 
Continued good news! Generally, the dredging operations have been running fairly smoothly with typical downtime for maintenance, outside of the 15-hour downtime on 11/08 for the repair of a broken sheave.
 
HDR and the County met with Rigid’s Project Manager on FRI morning to discuss progress and expected dredging completion date. Based on current dredging rates, it appears that the actual dredging may be completed by the end of the year. We’re all hoping for production to pick up, but current production metrics indicate that the end of the year may be the soonest they’ll be done with the dredging operations. Demobilization will follow and last a couple of weeks.
  • Boaters please stay clear of markers, the dredge pipe, all equipment, and the discharge area
 