The Dredge Report - 1/12/22
Posted on Jan 17th, 2022
Map shows section of river reworked thru Wed 1/12/22
Status Report 12Jan22
Rigid Constructors - Dredging Contractor
Daniel Garza Project Manager - HDR Engineering, Inc, Owner’s-Engineer
Based on daily reports, the following metrics have been calculated:
LF (Linear Feet) = 7,740 (79.8% of 9,700)
CY (Cubic Yards) = 311,538 (86.0% of 362,163) - Total volume will be adjusted when quantity calculations are completed.
Waves/currents have continued to hinder progress. Rigid was able to accomplish dredging only on Thu and Fri of this time period.
Rigid is gearing up to move back upriver to the GIWW and begin dredging south. This should alleviate challenges and waves and currents that they’re experiencing at the mouth of the river. They may begin that effort this week.
The County has calculated and provided a quantity of the additional material to Rigid, and are waiting to received concurrence on that quantity. There are required discussions to understand and agree to the quantities.
- Boaters please stay clear of markers, the dredge pipe, all equipment, and the discharge area.